Bank Holidays

F

Feeon

In MS Project 2003 is there anything I can do to alert the user where weeks
including bank holidays will automatically recognise when a resource is
allocated for more than 4 working days.

Thanks
 
R

Rod Gill

Usual practice is to:
Select Tools, Change Working Time
In the Standard calendar set the relevant holidays to non-working.

All tasks spanning the holidays are now automatically delayed by the
non-working days.
 
F

Feeon

Thanks for your quick response Rod, I know it was a bit of a basic question
but I'm just learning about Project

Thanks
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top