Is it possible to have the bar chart show the original estimated START/FINISH
(which it does already) and the Baseline START/FINISH (which I'm using as my
actual). In other words, two bars for the same task and I don't mean the
black bar you get when you put % complete.
Example:
START/FINISH 3/1/07-4/1/07
Baseline START/FINISH 5/1/07-6/1/07
(which it does already) and the Baseline START/FINISH (which I'm using as my
actual). In other words, two bars for the same task and I don't mean the
black bar you get when you put % complete.
Example:
START/FINISH 3/1/07-4/1/07
Baseline START/FINISH 5/1/07-6/1/07