John Sitka said:
Thanks, I don't get it
Barstyles - > Tasks (the first one)
Show for .... Tasks = Normal
on the TEXT tab I have
LEFT = Name
RIGHT = Remaining Work
Barstyles - > External Tasks (near the bottom of the list)
Show for .... Tasks = Extenal Tasks, Not Milestone
on the TEXT tab I have
LEFT = <nothing>
RIGHT = <nothing>
The External Tasks show
LEFT = Name
RIGHT = Remaining Work
If I specicaly add
LEFT = Resource Name
RIGHT = Duration
for example to the External Tasks Text tab.
Those values are supperimposed over top of
LEFT = Name
RIGHT = Remaining Work
??????
Thanks
John,
Wow, you're right, I never really played with it that much. Off hand I
can't explain what is going on but I do have a workaround. Try using a
spare flag to identify all external tasks (yeah I know, this is
redundant with the External Task field but stay with me here). Then set
up a custom bar for all the external/flag1 tasks. Finally, for the
Normal task bar set the "show for..." to be the following:
Normal, Not Flag1
If I have time I'll play around with it some more and try to figure out
why it does what it does. Maybe it's a bug that no one ever noticed or
bothered to report.
John
Project MVP