base calendar

G

greg tatchell

how do i get a printout of the non working time for a project, instead of
just teh base calendar?
using 2003 std
 
G

Gérard Ducouret

Greg,
Have you tried :
Views / Reports / Base calendar.... Preview ... and look at the different
pages if you have several calendars.

Gérard Ducouret
 
G

greg tatchell

thanks gerard, i was looking more to fine tune the chart. at the end of each
week i wanted to have a total of the hours worked that week for that task or
resource. sort of like to sub total tally each week. this is for production
to see what hours on each task.
 
G

greg tatchell

gerard, even though i have multiple calendars added to global, i can still
only see the base calendar in the reports/base calendar. none others show up.
 
G

Gerard

Thats because a project can only have one base calendar, the others will
be resource or task calendars - unless you chage the current base
calendar to another?
 
J

Jan De Messemaeker

A project can have scores of base calendars (don't know how many, never felt
a limitation).
It can only have one of these as a project calendar, but by Tools, change
working time, new, you can create as many base calendars if you like.
HTH
 
M

Manmeet Chaudhari

Hi,
If you want the total of hours worked per week on tasks by respective
resource then why not make use of resorue usage or task usage report.

Try if it helps.

Thanks and regards,
Manmeet Chaudhari
 