Base Calendars

A

Andrew Chia D-Biao

my new task (which using another base calendar, longer hours) link from the
previous task. Supposingly i want it to start on the new following day, but
the Project showed it to continue from the hours after 5pm. how can i specify
without setting constraint and the start date as this project has some delays
and is expecting some changes to happen soon
 
J

Jan De Messemaeker

Hi,

Suppose the predecessor task has working time till 17:00, and the successor
task hes working time tll 18:00 then Project will logically try to use the
time between 17:00 and 18:àà since it will schedule as soon as possible.
To avoid it you have to complete the link with a (in this example) 1 hour
lag
Task information, predecessors, fill in a lag of 1h.
HTH
 