Baseline cost not in summary task in Master Project

T

ThomasVike

I've inserted an existing project in a new project (to be a master file). In
the origional project file I have a 'summary task' to have an overview of a
hours, cost etc. of the project. The column 'Baseline Cost' shows the
cummulative baseline cost of the project on the summury line.

However this same box (Baseline cost of summary task (=project), is '0' in
the master file... Whereas the tasks themselves have baseline cost listed.
All other (not baseline based) columns are shown correctly in the summary
line, e.g. ACWP.

How can I show the Baseline Cost correctly in the Summury task of an
inserted project in a master file?
 
S

soniva

Hi!

The solution to your problem is to save the baseline on the maste
(consolidated) project as well as in the sub-projects. This gives yo
the baseline cost without having to "open" up the sub-projects.

Br,



Iva
 