J
Jrufin
Hi,
We have a project wherein we are entering the actuals (work hrs)
continuously. Now the problem is we already entered 2 months of actual data
on the project but now we want to re-baseline the schedule to September 3,
2007. How can we do it because we already entered all data since then and we
want to compare the current/actual cost and labor versus the supposedly
baseline date of the project dated Sept 3, 2007 (original start date)?? Take
note, we didn't save any baseline eversince.
I have an archive of our old schedule dated Sept 3, 2007, should I start
from scratch, edit the old schedule we have (dated Sept 3, 2007), save a
baseline as of Sept 3 then enter ALL the actuals again?? It will be a big
work, I hope there is a another way to do it, so please help.
Thanks!
We have a project wherein we are entering the actuals (work hrs)
continuously. Now the problem is we already entered 2 months of actual data
on the project but now we want to re-baseline the schedule to September 3,
2007. How can we do it because we already entered all data since then and we
want to compare the current/actual cost and labor versus the supposedly
baseline date of the project dated Sept 3, 2007 (original start date)?? Take
note, we didn't save any baseline eversince.
I have an archive of our old schedule dated Sept 3, 2007, should I start
from scratch, edit the old schedule we have (dated Sept 3, 2007), save a
baseline as of Sept 3 then enter ALL the actuals again?? It will be a big
work, I hope there is a another way to do it, so please help.
Thanks!