chazman
I am having a problem with the Baseline Work value displayed for a summary
task. The individual Baseline Work values for the subtasks are all equal to
the Work value as expected; however, the summary task value for Baseline Work
is not correct. It is close to the correct value but not equal. Worse yet,
on some summary tasks the Baseline Work value is correct. I have tried
reentering the summary task and letting the summary values be recalulated
with no success. The summary task Work value always seems to be correct.
Thanks for any help or suggestions that anyone can provide.
task. The individual Baseline Work values for the subtasks are all equal to
the Work value as expected; however, the summary task value for Baseline Work
is not correct. It is close to the correct value but not equal. Worse yet,
on some summary tasks the Baseline Work value is correct. I have tried
reentering the summary task and letting the summary values be recalulated
with no success. The summary task Work value always seems to be correct.
Thanks for any help or suggestions that anyone can provide.