BCWS & BCWP updates

J

Julz

Why doesn't BCWS and BCWP update in value when I apply % complete? The
project baseline is saved and the task has a valid number of days and a
resource assigned. using project 2002.
 
G

Gérard Ducouret

Hello Julz,
Did you update the Status date ?
Project / Project information...

Gérard Ducouret
 
P

Pratta

Hi Julz
And is your schedule baselined and a resource cost recorded in the resource
sheet?

Regards...............Pratta
 