J
Julz
Why doesn't BCWS and BCWP update in value when I apply % complete? The
project baseline is saved and the task has a valid number of days and a
resource assigned. using project 2002.
project baseline is saved and the task has a valid number of days and a
resource assigned. using project 2002.