It doesn't break it down by resource but doesn't the Variance table do
exactly that? If your links are set up properly you should see a variance
of plus or minus X days in the finish milestone, relfecting whether as of
the moment you are ahead of or behind schedule by that amount? Even if
the finish is way out in the future, if it's currently showing a 10 day
variance, that means as of right now, if everything from now on goes as
currently scheduled you'll finish 10 days late. That implies in turn that
as of the moment you are 10 days later than where you should be, ie, have
done 10 days LESS work than you had planned to do by now.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Hi Jack. Thanks for the link - its very useful. However, its more than I
actually need. I am interested in a simple snapshot that states: for a
given date (the project status date) how many days effort behind or ahead
are we.
E.g. A task has 10 days estimated effort, with 1 resource assigned. 5
days in the task should have 5 days effort against it. The figure that I
expect to get is 0. We are exactly on schedule. If only 4 days are
complete against the task then I should get 1 day behind. If 6 days
are
complete against the task I should get 1 day ahead.
Is there an "out of the box" report that can show that or do I need to
use a macro similar to the one that you have identified?
Thanks again!
--
McGeeky
http://mcgeeky.blogspot.com
Yes, Using earned value approaches will show this. I have a very simple
example of how to do something similar here: