J
Johnny Bravo
Hey all,
I'm still relatively new to MS Proj 2007 so bear with me =/
I have entered a number of projects which I've been using for time planning
purposes and general review of estimated labor costs. We use Peachtree to
track actual costs (invoices, payroll, purchases...)
My question is this:
If we want to track those Peachtree costs in Project 2007, what way would
you recommend as the easiest / preferred?
Currently I compose a job ledger cost printout from Peachtree. Back out
some miscategorized numbers, and have my base cost (minus labor)> We use
ADP for payroll, but prefer to use Assumed cost numbers per employee
(example $20/hour for labor --includes overhead charge)
If we want to compare estimated cost for a phase, we look at Project and it
tells us $1000 (5 men x 10h/day @ $20/hr x 1 day = $1000)
When the job goes over: our time sheets have 2 days... we have a loss of
$1000 for that phase. That's a simplified version.
How do I go back to show that in Project?
Right now we just build an excel sleet and manually enter the numbers
showing over and underruns in Excell, but that seems like a waste no using
project to track the cost...
What would you suggest?
Should I change all our entered labor resources to budget items and enter
all the time sheets from peachtree into Project? (seems like a lot of work)
I'm still relatively new to MS Proj 2007 so bear with me =/
I have entered a number of projects which I've been using for time planning
purposes and general review of estimated labor costs. We use Peachtree to
track actual costs (invoices, payroll, purchases...)
My question is this:
If we want to track those Peachtree costs in Project 2007, what way would
you recommend as the easiest / preferred?
Currently I compose a job ledger cost printout from Peachtree. Back out
some miscategorized numbers, and have my base cost (minus labor)> We use
ADP for payroll, but prefer to use Assumed cost numbers per employee
(example $20/hour for labor --includes overhead charge)
If we want to compare estimated cost for a phase, we look at Project and it
tells us $1000 (5 men x 10h/day @ $20/hr x 1 day = $1000)
When the job goes over: our time sheets have 2 days... we have a loss of
$1000 for that phase. That's a simplified version.
How do I go back to show that in Project?
Right now we just build an excel sleet and manually enter the numbers
showing over and underruns in Excell, but that seems like a waste no using
project to track the cost...
What would you suggest?
Should I change all our entered labor resources to budget items and enter
all the time sheets from peachtree into Project? (seems like a lot of work)