C
cr113
I'm new to Microsoft Project but I'm very familiar with writing macros
in VBA. I need to update start and finish dates in a project on a
weekly basis and I'm wondering what is the best way to do this.
Suppose you had a project that looks like this:
ID Start Finish
1 1/1/2009 3/1/2009
If I wanted to change the Start date to 2/1/2009 for example, how can
I do this (other that typing it in)? I was thinking there might be 2
ways. One way might be to manually import tha data assuming Project
has some sort of Import feature. Another way might be to write a
macro.
I'll be receiving weekly data in Excel that looks something like this:
ID Start Finish
1 2/1/2009 3/1/2009
2 4/1/2009 8/1/2010
So my question is this. If you had to update to your Project file
weekly, given the data I have to work with, how would you do it? I'm
using Microsoft Project 2007.
Thanks!
in VBA. I need to update start and finish dates in a project on a
weekly basis and I'm wondering what is the best way to do this.
Suppose you had a project that looks like this:
ID Start Finish
1 1/1/2009 3/1/2009
If I wanted to change the Start date to 2/1/2009 for example, how can
I do this (other that typing it in)? I was thinking there might be 2
ways. One way might be to manually import tha data assuming Project
has some sort of Import feature. Another way might be to write a
macro.
I'll be receiving weekly data in Excel that looks something like this:
ID Start Finish
1 2/1/2009 3/1/2009
2 4/1/2009 8/1/2010
So my question is this. If you had to update to your Project file
weekly, given the data I have to work with, how would you do it? I'm
using Microsoft Project 2007.
Thanks!