Blackout dates in Project 2002

K

kcameron

How can I establish blackout dates for specific tasks in Project 2002. Need
ability to prevent Project from scheduling specific tasks on specific dates
 
J

JackD

Go to Tools menu /change working time,
select the dates on the calendar and click the "non-working time" button.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project

..
kcameron said:
How can I establish blackout dates for specific tasks in Project 2002. Need
ability to prevent Project from scheduling specific tasks on specific
dates
 
K

kcameron

Thanks JackD, but won't that make those dates non-working times for all
tasks. I just want to specify for a certain tasks that can't be performed at
year end.
 
S

Sarah

You can create a custom calendar with the blackout dates and apply it
to those tasks.
 
J

JackD

Yep. Make a new calendar with the dates, Then select the tasks (hold down
the control key to select multiple tasks) and hit SHIFT+F2 to open the task
dialog box. Go to the advanced tab and set the calendar to the one you want.
This functionality is only available in more recent versions of project. I
think Proj 2000 was the first version to have task calendars, but I may be
wrong.
 