I'm doing a plan for an 11 month project, but want to blank out two 2 week
periods where no activity can take place i.e. any tasks that fall within that
timescale will automatically move their dates to the right (outside of the
specified dates).

Any way of doing this?
 
J

JulieS

Hi Stuart,

I suggest making the two week period of time nonworking time in the
project calendar. (Tools > Change Working Time).

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
S

Stuart

I've done that and it looks good. Many thanks.

JulieS said:
Hi Stuart,

I suggest making the two week period of time nonworking time in the
project calendar. (Tools > Change Working Time).

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top