S
Stuart
I'm doing a plan for an 11 month project, but want to blank out two 2 week
periods where no activity can take place i.e. any tasks that fall within that
timescale will automatically move their dates to the right (outside of the
specified dates).
Any way of doing this?
periods where no activity can take place i.e. any tasks that fall within that
timescale will automatically move their dates to the right (outside of the
specified dates).
Any way of doing this?