C
callawayman
We just can't get a 37.5 hour week calendar to work in MSP2000. We have
changed the options to 7.5h per day, 37.5h per week, 5 days a week and
the working time is amended reflect this timescale. There is no problem
when adding tasks - dates and times are correct - but as soon as we add
predecessor(s) Project seems to go back to the Standard calendar and
reschedule tasks to start at 08:00. This shortens the day by half an
hour putting the whole schedule out of sync. What are we doing wrong
here?
changed the options to 7.5h per day, 37.5h per week, 5 days a week and
the working time is amended reflect this timescale. There is no problem
when adding tasks - dates and times are correct - but as soon as we add
predecessor(s) Project seems to go back to the Standard calendar and
reschedule tasks to start at 08:00. This shortens the day by half an
hour putting the whole schedule out of sync. What are we doing wrong
here?