B
bkoren
I had a large project with assigned resources and baseline hours. This was
too large to manage so I broke it down into 2 smaller projects. The way I
did this was by making a copy of the larger project then deleting the tasks
for that I didn't want in either project. I did not unassign resources. I
kept the first project under its original name and renamed the second
project. Now when I level the second project my resources cannot start until
after they have completed their assignment on the original project. The
problem is they no longer have tasks on the original project. For some
reason my second project thinks they are still assigned to the first project.
Any suggestions on how to resolve this problem?
Thanks,
Barb
too large to manage so I broke it down into 2 smaller projects. The way I
did this was by making a copy of the larger project then deleting the tasks
for that I didn't want in either project. I did not unassign resources. I
kept the first project under its original name and renamed the second
project. Now when I level the second project my resources cannot start until
after they have completed their assignment on the original project. The
problem is they no longer have tasks on the original project. For some
reason my second project thinks they are still assigned to the first project.
Any suggestions on how to resolve this problem?
Thanks,
Barb