I have a large project with resources and baseline hours assigned. it was
too large to manage so I broke it down into smaller projects by making a copy
of the project and deleting the tasks I did not want in each given smaller
project. I still kept tasks under the name of the larger project. So
essentially I have:
Large_ Project
Project A
Project B
When I go to level Project A my resources appear to still be commited to
Large_Project even though I deleted the tasks along with the resources. When
I look at the resource usage it in fact says that the resource is committed
to both projects. When I look at Large_Project these resources are not there.
Any suggestions on how I can clean this up?
thanks,
Barb
too large to manage so I broke it down into smaller projects by making a copy
of the project and deleting the tasks I did not want in each given smaller
project. I still kept tasks under the name of the larger project. So
essentially I have:
Large_ Project
Project A
Project B
When I go to level Project A my resources appear to still be commited to
Large_Project even though I deleted the tasks along with the resources. When
I look at the resource usage it in fact says that the resource is committed
to both projects. When I look at Large_Project these resources are not there.
Any suggestions on how I can clean this up?