R
RB
Hi,
One of the column in the project plan is Business Day, which requires manual
input .
The relationship between Business Days and Calendar Days for month 1 is
generally different to the relationship between Business Days and Calendar
Days for month 2. e.g.
In Oct, 3rd Oct Fri is BD 3
In Nov, 3rd Nov Mon is BD1 (as Nov 1 and 2 fall on weekend)
In Dec, 3rd Dec is BD 3
In Jan, 3rd Jan is a non working day as it is on weekend
Thus, every month BD column requires a manual entry. Is it possible to have
a formula which calculates Business Day based on working calendar day?
Thanks,
One of the column in the project plan is Business Day, which requires manual
input .
The relationship between Business Days and Calendar Days for month 1 is
generally different to the relationship between Business Days and Calendar
Days for month 2. e.g.
In Oct, 3rd Oct Fri is BD 3
In Nov, 3rd Nov Mon is BD1 (as Nov 1 and 2 fall on weekend)
In Dec, 3rd Dec is BD 3
In Jan, 3rd Jan is a non working day as it is on weekend
Thus, every month BD column requires a manual entry. Is it possible to have
a formula which calculates Business Day based on working calendar day?
Thanks,