H
hintze1
I have resources who cannot work on the project the first 3 buinsess days
each month. I tried using reoccurring non working days but it only appears to
apply to actual days of the month not business days i.e. if the 1'st is on
Sunday it does not move the non working day to Monday, the first business
day, so my resource shows avaialble for work. Is there an alternative to
creating a unique calendar for these resources? Thanks.
each month. I tried using reoccurring non working days but it only appears to
apply to actual days of the month not business days i.e. if the 1'st is on
Sunday it does not move the non working day to Monday, the first business
day, so my resource shows avaialble for work. Is there an alternative to
creating a unique calendar for these resources? Thanks.