Calculate complete dates

D

deluth

I'm currently using MSP 2003. I track tasks by % complete and also use the
status indicator to tell me if the task is on track.

Is there a way I can "calculate" when the task would complete based on the
percentage complete? For example if the task is 30%, but it's not on track
(status indicator is red), can Project calculate for me when the task would
be 100% based on the fact that it's 30% today?

Thank you!
 
R

Rod Gill

You need to move to tracking by Actual Duration. For each task enter:
Actual Start Date
Actual Duration
then update Remaining Duration

% complete is calculated for you.

More accurate again is to track actual work in a usage view or use a time
sheet system that directly updates .mpp files.
 
D

DavidC

Hi,

Using the tracking toolbar, there is a button "Reschedule work". Once you
have entered the % complete, click on that button will split the task at the
percentage complete and reschedule the remaining portion of the task tom
start at the status date.

Hope this helps

Regards
DavidC
 