O
otterit
I have a single task (Project Manager) in my project that has 158.5 hours
remaining. I am trying to represent the 158.5 hours where the person assigned
is only working for 4 hours a week. The other people (tasks) work for 40
hours a week.
I tried using the instructions I found on
http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=347, but they're
not working.
I selected the task I need to modify called Project Manager, Clicked Tools,
Change Work Time, Highlighted Mon - Fri, hit Options, Changed Hours per Day
to 1, Hours per week to 4, Clicked OK, made sure Non-Default was selected,
and hit OK.
Nothing Happened. The Project Manager task still ends in 158.5 hours instead
of being stretched over a couple weeks.
Can some explain what I might be doing wrong??
Thanks!!
remaining. I am trying to represent the 158.5 hours where the person assigned
is only working for 4 hours a week. The other people (tasks) work for 40
hours a week.
I tried using the instructions I found on
http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=347, but they're
not working.
I selected the task I need to modify called Project Manager, Clicked Tools,
Change Work Time, Highlighted Mon - Fri, hit Options, Changed Hours per Day
to 1, Hours per week to 4, Clicked OK, made sure Non-Default was selected,
and hit OK.
Nothing Happened. The Project Manager task still ends in 158.5 hours instead
of being stretched over a couple weeks.
Can some explain what I might be doing wrong??
Thanks!!