K
King Kong
Hi
I made aproject plan with a rough estimation what person is doing what.
I did for the entire lifecycle (we are at the start of the project).
The ressources were allocated to me in a manner
50% A
30% B
80% C
etc.
I made calendars for these guys and planned their trainings, holidays etc.
So this is setup properly.
Now I would like to know how many hours overall, or even better per ressource,
I need from Date A to Date B (for example Phase Inception).
Any idea how to get this out of project?
Thanks
Kay
I made aproject plan with a rough estimation what person is doing what.
I did for the entire lifecycle (we are at the start of the project).
The ressources were allocated to me in a manner
50% A
30% B
80% C
etc.
I made calendars for these guys and planned their trainings, holidays etc.
So this is setup properly.
Now I would like to know how many hours overall, or even better per ressource,
I need from Date A to Date B (for example Phase Inception).
Any idea how to get this out of project?
Thanks
Kay