A
Ali
Hello,
MS Project 2003:
I have one big enhancement ex. EDD2000 and then 23 enhancements that make up
EDD2000.
So on my MS project plan, on the first line under task is EDD2000 and when
you "expand" it you see all 23 enhancements which can all be expanded to see
their tasks.
Now many of the 23 enhancements start and finish at the same time..
What I want see is when I don't expand EDD2000 I want to see in the duration
column the total duration ( all 23 enhancements duration added up)..
Do I use the "Predecessor" column to do this action??
Thanks
MS Project 2003:
I have one big enhancement ex. EDD2000 and then 23 enhancements that make up
EDD2000.
So on my MS project plan, on the first line under task is EDD2000 and when
you "expand" it you see all 23 enhancements which can all be expanded to see
their tasks.
Now many of the 23 enhancements start and finish at the same time..
What I want see is when I don't expand EDD2000 I want to see in the duration
column the total duration ( all 23 enhancements duration added up)..
Do I use the "Predecessor" column to do this action??
Thanks