Problem with project calendar and working time.
I have a project calendar running on a number of low level schedules,
however if I change the working time on calendar, it only makes the changes
for that schedule. How can I change the working time on a project calendar
and get the changes to apply to wherever that project calendar is used. The
schedules are all linked to a resource schedule that also uses the project
calendar.
I have a project calendar running on a number of low level schedules,
however if I change the working time on calendar, it only makes the changes
for that schedule. How can I change the working time on a project calendar
and get the changes to apply to wherever that project calendar is used. The
schedules are all linked to a resource schedule that also uses the project
calendar.