Calendar View - start from sunday

  • Thread starter גילי
  • Start date
×

גילי

Hi

In Project 2002 (Offline) I'm Trying to customize a Calendar view, that it
will show 5 days a week starting on sunday (instead of monday) without any
success.
The project calendar includes sundays as working days and in calendar
options (Tools > Options > Calendar) work week starts on sunday.

Will appreciate help.

Thanks,

Gili
 
J

JulieS

Hi Gili,

Sorry to say this but I'm afraid the option "Show week with 5 days" seems to
only show Monday through Friday, despite changes in the working time (Sunday
through Thursday for example.)

I hope this helps.

Julie

Visit http://project.mvps.org/ for the FAQs and additional information about
Microsoft Project
 
×

גילי

Thanks a lot Julie.

Gili

JulieS said:
Hi Gili,

Sorry to say this but I'm afraid the option "Show week with 5 days" seems to
only show Monday through Friday, despite changes in the working time (Sunday
through Thursday for example.)

I hope this helps.

Julie

Visit http://project.mvps.org/ for the FAQs and additional information about
Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top