D
DavidC
Hi,
Thought this might be a salutory lesson for some.
My project has a number of work fronts, of which one area works one 10 hour
shift whilst everywhere else they work 2 10 hour shifts. By not allocating
the 10 hour shift calendar to those tasks being carried out by the resoruces
working 1 10 hour shift I kept getting changes to durations being made
automatically after changing the duration on one task, even those tasks were
not directly related other than through the resources. Problem was though
that on those tasks they used a resource which was used for the 2 10 hour
shifts (crane) and that was driving the work values based on the duration
which was initially set to the 2 10 hour shift calendar.
Setting the calendar on the task that related to the area, the summary days,
durations and related work values all lined up properly.
So simple a solution yet I overlooked not specifically setting the task
calendar and leaving it to default to the project calendar.
Follow the basics and do not shortcut.
For what it is worth,
regards
DavidC
Thought this might be a salutory lesson for some.
My project has a number of work fronts, of which one area works one 10 hour
shift whilst everywhere else they work 2 10 hour shifts. By not allocating
the 10 hour shift calendar to those tasks being carried out by the resoruces
working 1 10 hour shift I kept getting changes to durations being made
automatically after changing the duration on one task, even those tasks were
not directly related other than through the resources. Problem was though
that on those tasks they used a resource which was used for the 2 10 hour
shifts (crane) and that was driving the work values based on the duration
which was initially set to the 2 10 hour shift calendar.
Setting the calendar on the task that related to the area, the summary days,
durations and related work values all lined up properly.
So simple a solution yet I overlooked not specifically setting the task
calendar and leaving it to default to the project calendar.
Follow the basics and do not shortcut.
For what it is worth,
regards
DavidC