Calendars

A

amaia

Hello to all!

We are going to use Project Server 2003 in our company, we are testing
it and we have a question:

We have created a new calendar with someday festive and assign it to
one project, project considers in that day does not work, so it is ok.
But, when we assign an enterprise resource to a task of that
project, if in the calendar of the resource that day is a working that day,
Project changes the programming and in that day the project works.

It is like this? It is well?

Thank you very much and sorry for my english
 
M

Mike Glen

Hi amaia ,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 
S

Steve House [MVP]

That is exactly the way it's supposed to work. The task schedule will
always follow the resource's schedule unless you override it. If the
resource is going to take the holiday off, you need to insure his resource
calendar is updated.
 
A

amaia

Thanks a lot,

Amaia

Steve House said:
That is exactly the way it's supposed to work. The task schedule will
always follow the resource's schedule unless you override it. If the
resource is going to take the holiday off, you need to insure his resource
calendar is updated.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top