amaia
Hello to all!
We are going to use Project Server 2003 in our company, we are testing
it and we have a question:
We have created a new calendar with someday festive and assign it to
one project, project considers in that day does not work, so it is ok.
But, when we assign an enterprise resource to a task of that
project, if in the calendar of the resource that day is a working that day,
Project changes the programming and in that day the project works.
It is like this? It is well?
Thank you very much and sorry for my english
We are going to use Project Server 2003 in our company, we are testing
it and we have a question:
We have created a new calendar with someday festive and assign it to
one project, project considers in that day does not work, so it is ok.
But, when we assign an enterprise resource to a task of that
project, if in the calendar of the resource that day is a working that day,
Project changes the programming and in that day the project works.
It is like this? It is well?
Thank you very much and sorry for my english