Hi, I’ve spent hours trying to find solutions to the following
problems,,,,hope someone can help with some or all. Thanks in advance
1. CALANDER DURATION PROBLEMS. I have around 20 MS project files, all
inserted/linked into a master file. In both files i have adjusted the
standard calender to 7 work hours. I also use a shared resource pool file,
with calender set to 7 work hours. Problem is when I assign 1 day to a task
in any project file, the master project regards it as 0.88 day., meaning the
master project still regards a day as 8 hours . this happens for all task,
whether resources are assigned or not.
2. SAVING FORMATTED TEXT IN 0 SUMMARY TASK NOTE....
a. When I enter a note in the summary task, and click OK to close the
dialogue box etc, it saves formatting OK. BUT when i save the whole doc,
formatting is removed, and reverts to normal unformatted txt. Formatting is
saved fine in other task, just not the summary task.
3. INSERTING MULTIPLE DOCS TO A TASK...anyone know how to do this?? I’m
finding project will only allow one document linked
4. SET DURATION TO 1 DEC POINT...the duration column in gant chart defaults
to 2 decimal points, eg 1.56 days. Anyone know how to change to 1 or 0
decimal points??
5. PRINT HORIZONTAL READING LINES ON GANT CHART CALENDER SECTION. Would love
to know if this is possible, so its easy to see/align tasks with their
calander details when looking at printouts.
6. PASSWORD/ACCESS PROTECTION ON FILES...I cant see how to do this...like in
excel or word etc. I’m needing to give password protection for opening a
document, and editing a document.
problems,,,,hope someone can help with some or all. Thanks in advance
1. CALANDER DURATION PROBLEMS. I have around 20 MS project files, all
inserted/linked into a master file. In both files i have adjusted the
standard calender to 7 work hours. I also use a shared resource pool file,
with calender set to 7 work hours. Problem is when I assign 1 day to a task
in any project file, the master project regards it as 0.88 day., meaning the
master project still regards a day as 8 hours . this happens for all task,
whether resources are assigned or not.
2. SAVING FORMATTED TEXT IN 0 SUMMARY TASK NOTE....
a. When I enter a note in the summary task, and click OK to close the
dialogue box etc, it saves formatting OK. BUT when i save the whole doc,
formatting is removed, and reverts to normal unformatted txt. Formatting is
saved fine in other task, just not the summary task.
3. INSERTING MULTIPLE DOCS TO A TASK...anyone know how to do this?? I’m
finding project will only allow one document linked
4. SET DURATION TO 1 DEC POINT...the duration column in gant chart defaults
to 2 decimal points, eg 1.56 days. Anyone know how to change to 1 or 0
decimal points??
5. PRINT HORIZONTAL READING LINES ON GANT CHART CALENDER SECTION. Would love
to know if this is possible, so its easy to see/align tasks with their
calander details when looking at printouts.
6. PASSWORD/ACCESS PROTECTION ON FILES...I cant see how to do this...like in
excel or word etc. I’m needing to give password protection for opening a
document, and editing a document.