Calender View Content

M

morrisC

VERSION 2003: Is there any way to modify the info shown in the calander view?
All I want is the task name, I don't want the duration and I'd love to color
code items or change font size.

If not available in version 2003 is it available in 2007?
 
M

Mike Glen

Hi Morris,

Welcome to this Microsoft Project newsgroup :)

The calendar view is rather limited in customization. From Format/Bar
Styles, select non-critical and in the Text section, just delete the
Duration field. Repeat for critical and other task types as you wish. The
only say you have in fonts and colours is a single font/colour for each task
type as listed. 2007 is no different.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
M

morrisC

Thanks that was great help.

Mike Glen said:
Hi Morris,

Welcome to this Microsoft Project newsgroup :)

The calendar view is rather limited in customization. From Format/Bar
Styles, select non-critical and in the Text section, just delete the
Duration field. Repeat for critical and other task types as you wish. The
only say you have in fonts and colours is a single font/colour for each task
type as listed. 2007 is no different.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top