Ditto on what Steve said. Please do not confuse work and duration which are
two different things. I can do 10hours of work with a duration of 5 days (40
hours) with an assigned units of 25%.
To directly address your question on <XML>
Task types (fixed work or units or duration) can be found on the advanced
tab of the project information dialog box. Select the Task Information icon
from the toolbar or double click on a task. Pull the advanced tab.
In the XML output, task type is contained under <Tasks><Task> and the field
is <Type>n<Type> where n is an integer representing Task Type
0=Fixed Units
1=Fixed Duration
2=Fixed Work
Tasks may also be <EffortDriven>
0=Non-effort driven task
1=Task is effort driven
A fixed work task is effort driven by default and cannot be changed by
project...careful if you are changing that in the XML. I did this
investigation using Project2007 Prof, you will need to look carefully for
your specific version of Project although I expect these two fields did not
change.
Further information about task types and effort driven status is available
in "Help"
--
If this post was helpful, please consider rating it.
Jim
It's software; it's not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project