Can I set up a RAG status column against tasks in Project 2003?

M

Marcus M

Hi

Is it possible to set up a RAG status column in Project Professional 2003
please?

Cheers
Marcus M
 
J

JulieS

Hi Marcus,

The short answer is yes. You can customize spare (Text1, Number1, etc.)
fields in Project with graphic indicators.

You'll first need to define what criteria you wish to use for the status
(schedule variance, cost variance, work variance etc.) and then create
the fields to show the graphic indicators.

A couple of references to get you started:

Try a google group search on this newsgroup for "RAG" or "Stop Light"

See Mike Glen's article # 15 - Customizing Fields available from the URL
below:

http://project.mvps.org/mike's_tutorials.htm

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
G

Gérard Ducouret

Hi Marcus,

You can do such a status column by your own, with a formula
IIF(condition,True,False) but have you tried to insert the "Status
indicator" column: Insert / column....
Hope this helps,

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top