Hi Marcus,
The short answer is yes. You can customize spare (Text1, Number1, etc.)
fields in Project with graphic indicators.
You'll first need to define what criteria you wish to use for the status
(schedule variance, cost variance, work variance etc.) and then create
the fields to show the graphic indicators.
A couple of references to get you started:
Try a google group search on this newsgroup for "RAG" or "Stop Light"
See Mike Glen's article # 15 - Customizing Fields available from the URL
below:
http://project.mvps.org/mike's_tutorials.htm
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project