V
Vic W
In the real world Work and Duration are independent. I don't want MS Project
to calculate it for me. I really want to turn off the D-W-U calculator. Can
this be done?
No combination of Fixed Duration, Fixed Unit, Fixed Work & Effort Driven
Flag seems to give me what I want. A scheduling program where I can plan and
track duration and effort without one affecting the other in some wierd
predetermined non relevant way.
It is simply to clever --
None of the available settings seems to allow the manual setting of work and
duration as independent items. I really want to break the link. This is
possible in many other programs Open Plan for instance. Effort is distinct
from Duration.
The only way I can achieve this is to defined people as a Material Type
resource assume a single unit is a dy but then the work doesn't roll up
properly and other smart graphical features don't work properly.
I do not need automatic levelling or a smart duration/work calculator. I
need the system down dumbed down so that it behaves... Anyone got the answer?
VW
to calculate it for me. I really want to turn off the D-W-U calculator. Can
this be done?
No combination of Fixed Duration, Fixed Unit, Fixed Work & Effort Driven
Flag seems to give me what I want. A scheduling program where I can plan and
track duration and effort without one affecting the other in some wierd
predetermined non relevant way.
It is simply to clever --
None of the available settings seems to allow the manual setting of work and
duration as independent items. I really want to break the link. This is
possible in many other programs Open Plan for instance. Effort is distinct
from Duration.
The only way I can achieve this is to defined people as a Material Type
resource assume a single unit is a dy but then the work doesn't roll up
properly and other smart graphical features don't work properly.
I do not need automatic levelling or a smart duration/work calculator. I
need the system down dumbed down so that it behaves... Anyone got the answer?
VW