J
JPD
I have a project that originally was planned to finish 3/31/08. Some
requirements have changed and the new planned finsih is 6/31/08. I
would like the project to extend to the new finish date without having
to modify each task duration.
Is there a way a project will extend duration automatically using a
"weighted" duration and increasing to meet new finish date? I would
also like the resource allocation % to remain the same and spread over
the new duration.
Thanks for your help in advance!
requirements have changed and the new planned finsih is 6/31/08. I
would like the project to extend to the new finish date without having
to modify each task duration.
Is there a way a project will extend duration automatically using a
"weighted" duration and increasing to meet new finish date? I would
also like the resource allocation % to remain the same and spread over
the new duration.
Thanks for your help in advance!