K
kraus
I have noticed that levelling does not make the best uyse of a resources
time. I have a current project where I have a resource at 70% (3.5 days/wk)
who is not currently on any other project within the company. I have a task
at 5wds (7.14 days duration) that runs from Jan 11 - 21. This equates to
2.68wds during the week of Jan 9 and 2.32 wds during the week of Jan 16;
nothing else is being worked on that week. In fact, the entire month of
January is a mystery. The breakdown is as follows:
Week of Jan 2 - .32wds
Week of Jan 9 - 2.68wds
Week of Jan 16 - 2.32 wds
Week of Jan 23 - .25 wds
I thought levelling/MSP would ensure the resources are used to their full
potential each week and provide the shortest duration. But it doesn't appear
to be working that way.
Can someone please provide some insite on the levelling algorithm?
The tasks that I have outlined above should have been completed within the
first 3 weeks with time to spare.
dave
time. I have a current project where I have a resource at 70% (3.5 days/wk)
who is not currently on any other project within the company. I have a task
at 5wds (7.14 days duration) that runs from Jan 11 - 21. This equates to
2.68wds during the week of Jan 9 and 2.32 wds during the week of Jan 16;
nothing else is being worked on that week. In fact, the entire month of
January is a mystery. The breakdown is as follows:
Week of Jan 2 - .32wds
Week of Jan 9 - 2.68wds
Week of Jan 16 - 2.32 wds
Week of Jan 23 - .25 wds
I thought levelling/MSP would ensure the resources are used to their full
potential each week and provide the shortest duration. But it doesn't appear
to be working that way.
Can someone please provide some insite on the levelling algorithm?
The tasks that I have outlined above should have been completed within the
first 3 weeks with time to spare.
dave