M
Michael
Lets say I have 2 8hr task assigned to the same resource. Why cant I select
both task assign a start date of feb 1 and a finish date of feb 3 and have it
make both start and stop at the same time but do 50% on each.
Instead of doing the first 8hr task then the next 8hr task.
After all I selected the start date to be the same.
Thanks for the help
both task assign a start date of feb 1 and a finish date of feb 3 and have it
make both start and stop at the same time but do 50% on each.
Instead of doing the first 8hr task then the next 8hr task.
After all I selected the start date to be the same.
Thanks for the help