Hello,
I am having a problem displaying a custom Text1 field next to a bar in MS
Project 2007. I would like text such as "CDR" to appear to the left and
standard Finish to the right of a milestone. I tried the following:
- Within the Custom Fields window, I ensure Task is selected, then Rename
the "Text1" field.
- In the Rename Field window, I enter "CDR" and now see that "Text1" has
been replaced with "CDR (Text1)" in the Custom Fields window.
- I then double click on the bar of interest, select the Bar Text tab, and
select "Text1 (CDR)" within the Left entry. I'm not sure why the slight
change in the () location. The Right entry already displays "Finish" as
default.
The Finish date shows, but the custom text does not. What am I doing wrong?
Thanks for the help!
Pete.
I am having a problem displaying a custom Text1 field next to a bar in MS
Project 2007. I would like text such as "CDR" to appear to the left and
standard Finish to the right of a milestone. I tried the following:
- Within the Custom Fields window, I ensure Task is selected, then Rename
the "Text1" field.
- In the Rename Field window, I enter "CDR" and now see that "Text1" has
been replaced with "CDR (Text1)" in the Custom Fields window.
- I then double click on the bar of interest, select the Bar Text tab, and
select "Text1 (CDR)" within the Left entry. I'm not sure why the slight
change in the () location. The Right entry already displays "Finish" as
default.
The Finish date shows, but the custom text does not. What am I doing wrong?
Thanks for the help!