J
jkn
Hi all
I am puzzled as to why MS project (Professional 2002) doesn't allow
me to do what seems to be a simple process of dragging a task to start
on a specific date.
I realise that this is not 'best practice', but I want to create a task
with a given duration, and drag it to start at a particular time.
I do 'new task task', double-click, and enter a duration. I have "new
tasks is set to 'start on current date'" is set in the Options |
Schedule tab. So I have a task starting on today's date, with a 'start
no earlier that <today>' constraint. so far, so good.
I then clear this constraint, by setting the Constraint type to 'Start
as soon as' in the 'Advanced' tab. I press OK, and the constraint is
gone.
I then try to drag the task to a different date. Project doesn't allow
this, which seems to be contrary to what I have read.
I understand that this would set a constraint, and for my current
purposes that's OK. I'm almost using Project as a 'drawing tool' for
now.
There seems to be a conflict between a 'start date' (which I never
entered, but is presumably how Project originally scheduled the task),
and a 'start no earlier than' constraint (which seems to refer to the
date I dragged the task to).
If I'm right in that, , then my question becomes, "How can I remove the
'start date' constraint? There seems to be know way of doing this, only
manually changing it.
If there is a better way of doing this I'd love to know. I am teaching
myself ways of using Project as a proper scheduling tool but sometimes
doing things the 'dirty' way has its useful...
Thanks very much in anticipation
Jon N
I am puzzled as to why MS project (Professional 2002) doesn't allow
me to do what seems to be a simple process of dragging a task to start
on a specific date.
I realise that this is not 'best practice', but I want to create a task
with a given duration, and drag it to start at a particular time.
I do 'new task task', double-click, and enter a duration. I have "new
tasks is set to 'start on current date'" is set in the Options |
Schedule tab. So I have a task starting on today's date, with a 'start
no earlier that <today>' constraint. so far, so good.
I then clear this constraint, by setting the Constraint type to 'Start
as soon as' in the 'Advanced' tab. I press OK, and the constraint is
gone.
I then try to drag the task to a different date. Project doesn't allow
this, which seems to be contrary to what I have read.
I understand that this would set a constraint, and for my current
purposes that's OK. I'm almost using Project as a 'drawing tool' for
now.
There seems to be a conflict between a 'start date' (which I never
entered, but is presumably how Project originally scheduled the task),
and a 'start no earlier than' constraint (which seems to refer to the
date I dragged the task to).
If I'm right in that, , then my question becomes, "How can I remove the
'start date' constraint? There seems to be know way of doing this, only
manually changing it.
If there is a better way of doing this I'd love to know. I am teaching
myself ways of using Project as a proper scheduling tool but sometimes
doing things the 'dirty' way has its useful...
Thanks very much in anticipation
Jon N