Hi
Haven't been using Project 2002 for long, but I'm having problems
indenting a subtask, I get the following message:
"This outline change would create a circular relationship"
It advises checking the task's dependencies but to be honest I'm not
sure what I should be checking for. Any help would be magic.
Cheers