Error in Project 2003

G

Ginny

I keep getting this error message in Project 2003...anyone have any ideas on
how to fix?

"This outline change would create a circular relationship.
Indenting these tasks would create an illogical relationship with other tasks.
Check the task dependencies for the tasks from which you are indenting, and
then try again.â€

Thanks!
 
M

Mike Glen

Hi Ginny,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 48 - Summary Task Linking.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 