Dave Barr
I have a master project that has 5 projects inserted. I want all 5 projects
to have the same level of indentation so that I can minimize them and see
the true start and end dates for each project.
What happens is that my first 3 projects work just fine and then when I
insert the 4th project I can't outdent it to the same level as the others -
is basically indented under the 3rd project. Nothing I do changes this.
Then when I insert the 5th project it is once again indented one level
further again so it is a subproject of the 4th project.
Can anybody tell me if there is a setting I am missing or is this a bug?
Thanks
Dave
to have the same level of indentation so that I can minimize them and see
the true start and end dates for each project.
What happens is that my first 3 projects work just fine and then when I
insert the 4th project I can't outdent it to the same level as the others -
is basically indented under the 3rd project. Nothing I do changes this.
Then when I insert the 5th project it is once again indented one level
further again so it is a subproject of the 4th project.
Can anybody tell me if there is a setting I am missing or is this a bug?
Thanks
Dave