P
Paulo de Arruda Borelli
I'm trying to have Project Standard 2002 assign the same Start and End Dates
to a 16-hour task. But Project keeps calculating the End Date as one day
after the Initial Date. For example: if the Initial Day is Aug-13th and the
task duration is 16 hours, Project calculates the End Day as Aug-14th.
This is NOT the expected date since my calendar is a 24-hour one.
To reproduce this problem:
1) Create a new project
2) Assign the 24-hour calendar to the project (Project Menu/Project Info,
Calendar = 24-hour Calendar)
3) Create a task
4) Set the task duration to 16h (16 hours)
5) Project will set the End Date as one day after the Start Date.
What's wrong here?
Thank you in advance
Paulo Borelli.
to a 16-hour task. But Project keeps calculating the End Date as one day
after the Initial Date. For example: if the Initial Day is Aug-13th and the
task duration is 16 hours, Project calculates the End Day as Aug-14th.
This is NOT the expected date since my calendar is a 24-hour one.
To reproduce this problem:
1) Create a new project
2) Assign the 24-hour calendar to the project (Project Menu/Project Info,
Calendar = 24-hour Calendar)
3) Create a task
4) Set the task duration to 16h (16 hours)
5) Project will set the End Date as one day after the Start Date.
What's wrong here?
Thank you in advance
Paulo Borelli.