change cost table dates for multiple resources at one time

T

Twoods

I would like to change the cost table dates for multiple resources at one
time instead of typing in the dates individually. Cut and pasting these
dates in doesn't seem to work either.
 
M

Mike Glen

Hi Twoods,

I don't think this is possible from within Project, though it may be
possible to write some code. Try posting on the developer newsgroup. Please
see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information can be seen at this web address:
http://www.mvps.org/project/.

Mike Glen
Project MVP
 

Ask a Question