W
wdaschner
Hello,
I have entered data for a larger project - thereby using the default
duration units (--> days). Now I would need the durations of all the tasks
entered displayed and stored in "hours" instead of "days" (1 day=8hours
according to normal calendar). I assumed this could be easily done, but found
no way to change the display units in the whole duration or work column from
days to hours (e.g. "2 days" should read afterwards "16 hours")
Can you help me with that?
thanks and cheers,
Wolfgang
I have entered data for a larger project - thereby using the default
duration units (--> days). Now I would need the durations of all the tasks
entered displayed and stored in "hours" instead of "days" (1 day=8hours
according to normal calendar). I assumed this could be easily done, but found
no way to change the display units in the whole duration or work column from
days to hours (e.g. "2 days" should read afterwards "16 hours")
Can you help me with that?
thanks and cheers,
Wolfgang