D
DonO
Help!!! Please forgive my lack of the proper terms in this request for help
because I am brand new to Project and am using the 2003 version.
My goal is to “map†a new modification on 10-20 different units to establish
a standard for the Resources and Duration. I’m simply trying to log actual
man hours and the duration of each task.
All my “projects†begin with a standard listing of Tasks. So far the Tasks
have undergone very few changes. To date I’ve got 3 Projects in work
simultaneously. I update the progress daily by adding Resources and making
(h) entries in the Work column. Basically, none of the columns have any
predetermined values before beginning. I set up 8h per day M-F 40 hours a
week and 20 days a month.
In an effort to keep it simple, the columns I’m working with are Number1,
Task Name, % Complete, Duration, Actual Start & Actual Finish
I am having trouble with the Resource man hour data (h) entered in the Work
column. All previous entries made (h) change whenever I add another Resource
after I return to that Task to update. The total value (h) remains the same
for the Task but the various entries change. To minimize this, prior to
adding another Resource, I must first note the totals for each Resource then
go back and reenter the data to remain accurate.
I notice the % Complete updates automatically based on updating the Work
column. The only time I update this column is when the Task completes.
Therefore, I then enter 100%.
I enter dates in Actual Start columns each time I begin a Task and add a
Resource. I do not enter a date without assigning a Resource. All Resources
added are accompanied by their Actual Start date.
Thanks in advance to all who offer assistance.
because I am brand new to Project and am using the 2003 version.
My goal is to “map†a new modification on 10-20 different units to establish
a standard for the Resources and Duration. I’m simply trying to log actual
man hours and the duration of each task.
All my “projects†begin with a standard listing of Tasks. So far the Tasks
have undergone very few changes. To date I’ve got 3 Projects in work
simultaneously. I update the progress daily by adding Resources and making
(h) entries in the Work column. Basically, none of the columns have any
predetermined values before beginning. I set up 8h per day M-F 40 hours a
week and 20 days a month.
In an effort to keep it simple, the columns I’m working with are Number1,
Task Name, % Complete, Duration, Actual Start & Actual Finish
I am having trouble with the Resource man hour data (h) entered in the Work
column. All previous entries made (h) change whenever I add another Resource
after I return to that Task to update. The total value (h) remains the same
for the Task but the various entries change. To minimize this, prior to
adding another Resource, I must first note the totals for each Resource then
go back and reenter the data to remain accurate.
I notice the % Complete updates automatically based on updating the Work
column. The only time I update this column is when the Task completes.
Therefore, I then enter 100%.
I enter dates in Actual Start columns each time I begin a Task and add a
Resource. I do not enter a date without assigning a Resource. All Resources
added are accompanied by their Actual Start date.
Thanks in advance to all who offer assistance.