You'll find that if you have set the duration of Task X to some value and
then later indent tasks X1, X2, and X3 as children under it, the original
duration of X that you input will be overridden by a new duration calculated
from the durations of its children. All tasks with tasks indented under
them in the outline structure are summary tasks. The durations of summary
tasks are ALWAYS read-only calculated values. This reflects the fact that
in a properly designed project task list, the children represent the
components of their parent - the summary task Foundation has as its children
Dig Hole, Tie Rebar, Erect Forms, Pour Concrete, Remove Forms, etc -all the
various elements that have to be done to make a completed foundation. It's
logical that the duration of the parent is 100% a consequence of the
durations of all its pieces.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visithttp://
www.mvps.org/project/faqs.htmfor the FAQs
JulieS,
Thanks for the quick response... I learned from tinkering with the
hierarchial buttons that I can adjust the time so long as I don't
create a child that's dependent on any task above it or below it.
I simply highlighted my tasks and made them the same rank, at which
point the Duration, Start & End Dates fields were unlocked.
You literally have to assign duration, start and end dates 1 task at a
time (OR do not assign hierarchy till after you've set time
parameters). Which I would imagine is the proper and logical way of
creating tasks. My intentions were to create the tasks by name first
then modify their specs thereafter.
I hope this makes sense.
BTW, I launched the site you recommended and have bookmarked for later
retrieval.
Thanks so much for your help!
All the best,
JulieS wrote:
Hi PMAgony,
I am guessing that you are trying to change the duration of a summary
task. (A task with other task indented underneath it.) The durations of
summary tasks are calculated by Project based upon the amount of working
time from the start of the earliest subtask to the finish of the latest
subtask. If you create links between the subtasks, the duration of the
summary task will automatically change.
As you are new to Project, I suggest taking a read of fellow MVP Mike
Glen's excellent series of articles on MS Project. They can be found
through the following link:
http://project.mvps.org/mike's_tutorials.htm
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visithttp://project.mvps.org/for the FAQs and additional information
about Microsoft Project
Good Day All,
Project Virgin here... I just defined my outline under the tasks list
and unwittingly allowed Project to enter the default estimate time of
1day?. Sweet...
However, now that I am done entering tasks, I'd like to go back and
actually specify the duration of each task from 1day? say to, 2days.
Nothing I can do physically is allowing me to change the estimated
(1day?) alotment.
Can someone please tell me how I can make a manual change. I've tried
right-clicking the cell for options but its greyed out. Nothing in
the
menus that indicates where to adjust the duration either.
Any help is greatly appreciated!
All the best,- Hide quoted text -