P
Project Pooped!
I am new to microsoft Project ($400 training-worthless). I am working on a
project. I have finished one job. Most of my jobs are the exact same all
the way through, but with different ship dates. I want the same durations,
but when I change the Start and finish dates the duration dates do not
automatically adjust. Instead it just shows me being done with the next
project well in advance as it is using the previous projects dates. Is there
any way of NOT entering each start date manually?
project. I have finished one job. Most of my jobs are the exact same all
the way through, but with different ship dates. I want the same durations,
but when I change the Start and finish dates the duration dates do not
automatically adjust. Instead it just shows me being done with the next
project well in advance as it is using the previous projects dates. Is there
any way of NOT entering each start date manually?