changing units in the resource graph

S

Steph

I have changed the timescale on my resource graph to weeks but the units on
the side still say /d. These are material resources and I tried to change the
peak units and have been unsuccessful. Please help if you can. Thank you
 
P

Perfect Reign

I have changed the timescale on my resource graph to weeks but the units on
the side still say /d. These are material resources and I tried to change the
peak units and have been unsuccessful. Please help if you can. Thank you

The display of the Duration colum (is this what you're referring to?) has
nothing to do with the scale.

To change the duration colum, click on Tools -> Options

Click on the "Schedule" tab.

About halfway down, you'll see a section titled, "Scheduling options for..."

To the right of the words, "Duration is entered in..." you'll see a
drop-down list for time units. You can change this to minutes, hours,
days, weeks or months.


HTH!
 