V
vdz
Hello all,
Can anybody please explain to me how peak units in resource usage get
calculated? The idea is to use resource usage view for planning and
monitoring hours resources have spent already (actual work) and are likely
to spend (work) in the future and compare it with the original planning
(baseline work). I thought 40 hours a week is taken as 100 % peak units.
Therefore 32 hours would be 80% of peak units and so on..However, I seem to
experience strange and unexplainable behaviour. For example, if
planned/baselined work was 40 hours a week for a resource but he worked less
hours, peak units for the coming weeks became 92% in first 3 weeks and then
106% in the week after. Or if somebody did not work for a month because of
holiday, then the peak units in the coming four weeks became 127% and after
that peak units are 112% without any obvious reason.
I truly hope somebody out there can help.
Many thanks,
Vera
Can anybody please explain to me how peak units in resource usage get
calculated? The idea is to use resource usage view for planning and
monitoring hours resources have spent already (actual work) and are likely
to spend (work) in the future and compare it with the original planning
(baseline work). I thought 40 hours a week is taken as 100 % peak units.
Therefore 32 hours would be 80% of peak units and so on..However, I seem to
experience strange and unexplainable behaviour. For example, if
planned/baselined work was 40 hours a week for a resource but he worked less
hours, peak units for the coming weeks became 92% in first 3 weeks and then
106% in the week after. Or if somebody did not work for a month because of
holiday, then the peak units in the coming four weeks became 127% and after
that peak units are 112% without any obvious reason.
I truly hope somebody out there can help.
Many thanks,
Vera