Roland67 said:
Thank you for your input.
Jan, your correct in your comments. Tasks do take on a constraint when
manually entered rather than linked. And yes, they can be changed if a link
pushed them beyond that constraint.
John, I hear what you're saying. BTW, nice soapbox! This project's
customer wants to know tasks going all the way out to its proposed completion
in 2010. We do not have any blinders on to not expect changes in tasks past
2005. We are just required to plan as best we can.
Now back to the "slamming" (I like that term) start dates. Any other
suggestions as Jan has indicated the inclusion of constraints won't work?
Roland,
Did I misinterpret what is happening? I understood you to say that when
your subprojects were inserted into a master, some of the tasks slammed
over to the Project Start date of the master, however (and I had to
confirm this with my own test), this will only occur if the subprojects
are statically consolidated into the master (i.e. subprojects not linked
to the master). In a dynamically consolidated master, the tasks in each
subproject adhere to the Project Start date of their respective
subprojects.
Perhaps we need a re-statement of what is happening before we can offer
other suggestions.
By the way, I understand about customer wants. I just hope they are not
looking for detail planning of any tasks beyond 12 months. Tasks beyond
the rule-of-thumb 12 month window should be expressed as "planning
packages". That is, they have a rough idea of Duration and perhaps even
cost, but no details. As time marches on and those out-year planning
packages get within 3 months of the present, then they should be detail
planned.
Just for reference, I am a firm believer that the constraint types
"must-start-on" and "must-finish-on" should never be used. When you get
down to it, they defy reality. It is said there are only two certainties
in life. One of them has to do with "rendering unto Caesar" and the
other has to do with the grim reaper. The "best laid plans" do not fit
into either category. Oops, there I am on that soapbox again. Sorry.
John
Project MVP