N
New-PM
Hello...I'm using MS Project 2007 with a very complex project. I noted that
if I change or update a task date, the succeeding linked task dates are
highlighted in light blue.
This is very useful for finding broken or mis-connected links...however, is
there a way beyond changing a date in a cell to see all the cells that are
affected "downstream" of the one task? I know there is a relationship view
screen, but I really like the blue highlighted cells of affected tasks.
Thanks
if I change or update a task date, the succeeding linked task dates are
highlighted in light blue.
This is very useful for finding broken or mis-connected links...however, is
there a way beyond changing a date in a cell to see all the cells that are
affected "downstream" of the one task? I know there is a relationship view
screen, but I really like the blue highlighted cells of affected tasks.
Thanks